ANNUAL PLAN (2002-03)

(Rs in lakhs)

Sl.

No

Name of the Schemes

Estd. Cost (latest)

Cumltve Exp. Upto 3/97

Appd. Outlay IXth Pl.

Actual Exp. IXth Pl.

Spill Over to Xth Plan

Appd. Outlay (2002-07)

Proposed Outlay (2002-03)

Appd. Outlay (2002-03)

Compl. Target

I.A

Generation Schemes

(I)

Complated Schemes:

1.

DPH at Gangtok (4x1MW).

1134.29

0.00

850.00

1100.00

34.29

0.00

0.00

15.00

Completed

2.

Rathongchu H.E.P. (2x1.5MW)

1182.00

303.60

450.00

763.40

115.00

115.00

115.00

230.00

Rolling in Aug. 02

 

CSS component

1070.00

341.40

333.50

559.50

169.10

75.00

75.00

176.00

 
 

Total (State Plan)

2316.29

303.60

1300.00

1863.40

149.29

115.00

115.00

245.00

 

(a)

CSS component

1070.00

341.40

333.50

559.50

169.10

75.00

75.00

176.00

 

(II)

Spilled over to Xth Plan

         

PUREY

124.00

ABANDONED

 

1.

Lachung Phase-II(2x1.5MW) State

450.00

0.00

900.00

224.00

226.00

226.00

50.00

105.00

Xth Plan

 

CSS component

1630.00

0.00

0.00

300.00

1050.00

1050.00

350.00

300.00

Xth Plan

2.

Mangley HEP (2x0.5MW) State

70.00

0.00

396.00

45.00

25.00

25.00

5.00

25.00

Xth Plan

 

CSS component

630.00

0.00

0.00

200.00

430.00

430.00

195.00

200.00

Xth Plan

 

Total (Spilled over to Xth Pl)-S/P

520.00

0.00

1296.00

269.00

251.00

251.00

179.00

130.00

 
 

CSS component

1980.00

0.00

0.00

500.00

1480.00

1480.00

545.00

500.00

 

(III)

New Schemes for the Xth Plan

 

Capacity Addition in the Tenth Plan Under Generation

(a)

Relli Khola (5 MW) State Plan

1872.00

0.00

0.00

0.00

0.00

1872.00

380.00

200.00

Xth Plan

 

CSS component

2250.00

0.00

0.00

0.00

0.00

2250.00

600.00

500.00

Xth Plan

(b)

Rongli Khola (5 MW) State Plan

722.50

0.00

0.00

0.00

0.00

722.50

300.00

200.00

Xth Plan

 

CSS COMPONENT

2167.50

0.00

0.00

0.00

0.00

2167.50

500.00

450.00

Xth Plan

(c)

Ringyang (1 MW) State Plan

330.00

0.00

0.00

0.00

0.00

330.00

25.00

25.00

Xth Plan

 

CSS component

600.00

0.00

0.00

0.00

0.00

600.00

300.00

300.00

Xth Plan

(d)

Chatten (2 MW) State Plan

302.00

0.00

0.00

0.00

0.00

302.00

53.00

50.00

Xth Plan

 

CSS component

900.00

0.00

0.00

0.00

0.00

900.00

200.00

200.00

Xth Plan

(e)

SPDC

5000.00

0.00

0.00

250.00

0.00

4750.00

1500.00

50.00

 
 

Total-New Schemes

8226.50

0.00

0.00

250.00

0.00

7976.50

2258.00

525.00

 
 

CSS component

5917.50

0.00

0.00

0.00

0.00

5917.50

1600.00

1450.00

 

I.A

TOTAL (I+II+III)

11062.79

303.60

2596.00

2382.40

400.29

8342.50

2552.00

900.00

 
 

CSS component Outside (I.A)

8967.50

341.40

333.50

1059.50

1649.10

7472.50

2220.00

2126.00

 

I.B.

RENOVATION SCHEMES

(I)

Completed Schemes

(a)

Jali Power House (2.5MW)-S/P

166.00

0.00

166.00

293.50

0.00

0.00

0.00

0.00

3/2002

 

CSS component

420.00

0.00

420.00

402.00

100.00

100.00

100.00

100.00

 

(b)

Rognichu Stage-II (2.5MW) S/P

100.00

0.00

100.00

202.46

0.00

0.00

0.00

0.00

3/2002

 

CSS component

300.00

0.00

300.00

392.00

140.00

140.00

140.00

140.00

 
 

Total-(II)-State Plan

266.00

0.00

266.00

495.96

0.00

0.00

0.00

0.00

 
 

CSS component

720.00

0.00

720.00

764.00

240.00

240.00

240.00

240.00

 

(III)

New Ranovation Schemes

(a)

Upper Rongnichu State Plan

311.00

0.00

0.00

115.00

196.00

196.00

50.00

0.00

3/2002

 

CSS component (Gen)

727.00

0.00

0.00

0.00

727.00

727.00

200.00

0.00

 

(b)

Synch of Rimbi-I and Kalez in to S/G i/c Renovation and modernisation –SP

149.00

0.00

70.00

65.55

83.45

84.00

25.00

0.00

3/2002

 

CSS component

348.00

0.00

0.00

0.00

348.00

348.00

100.00

0.00

 
 

Total-(III)-State Plan

460.00

0.00

70.00

180.55

279.45

280.00

75.00

0.00

 
 

CSS Component

1075.00

0.00

0.00

0.00

1075.00

1075.00

300.00

0.00

 

(III)

New Renovation Schemes

             

0.00

 

(a)

Jali Power House (For next two Units)

150.00

0.00

0.00

0.00

0.00

150.00

50.00

0.00

Xth Plan

(b)

Replacement of Close conduct W/C system of Mini/Micro Hydel Schemes

320.00

0.00

270.00

0.00

0.00

320.00

50.00

0.00

Xth Plan

 

CSS component

2880.00

0.00

0.00

0.00

0.00

2880.00

500.00

0.00

 
 

Total-(IV)-State Plan

470.00

0.00

270.00

0.00

0.00

470.00

100.00

0.00

 

I.B.

RENOVATION SCHEMES (I to III)

1196.00

0.00

606.00

676.51

279.45

750.00

175.00

0.00

 
 

CSS component

4675.00

0.00

720.00

794.00

1315.00

4195.00

1040.00

240.00

 

I.C

REP. WORKS CAP. NATURE

500.00

0.00

500.00

384.10

0.00

500.00

120.00

15.00

 

I.D

PURCHASE OF POWER

0.00

0.00

0.00

0.00

0.00

2500.00

0.00

100.00

 

I.

GENERATION TOTAL (A+B+C)

12758.79

303.60

3702.00

3443.01

679.74

12092.50

2847.00

1016.00

 
 

CSS component (Gen)

13642.50

341.40

1053.50

1853.50

2964.10

11667.50

3200.00

2366.00

 

II

TRANSMISSION

1.

Providing power Infrast. For ind. Units at Setipul & Mamring-constr. Of 66/11 7.5 MVA S/S each at For. Alloy coml..

1580.00

0.00

1180.00

1255.46

324.54

324.54

324.54

25.00

Aug ‘02

2.

66 KV Diversion work of Kaleng, kamlet and Gelling.

128.00

0.00

128.00

50.00

78.00

78.00

78.00

0.00

3/2003

 

b 66 KV Namchi College (Kamrang)

140.00

0.00

140.00

65.00

75.00

75.00

75.00

0.00

3/2003

3.

66 KVA S/Sth each at Mangan & Chungthang

1600.00

0.00

100.00

0.00

0.00

400.00

200.00

0.00

Xth Plan

4.

66 KV Soreng-Sombaria Trans Lines and 2x2.5 MVA 66/11 KV Sub-station at Sombarla

800.00

0.00

150.00

0.00

0.00

400.00

300.00

0.00

Xth Plan

5.

Exten. Of 66 KV lines and S/S for upcoming Hotel at Pangthang

300.00

0.00

0.00

0.00

0.00

300.00

200.00

0.00

Xth Plan

6.

132 KV transmission network asso. With evacuation of powr from Rolep. Ralong, U/Ralong, Suntelltar and Chakhungchu Hydro-electric Projects.

5376.00

0.00

0.00

0.00

0.00

3000.00

0.00

0.00

Xth Plan

7.

Providing addl. Bays and augmentation of 66/11 KV 7.5 MVA S/s to 15 MVA S/s at Mamring & asso. Works

300.00

0.00

0.00

0.00

0.00

300.00

300.00

0.00

Xth Plan

8.

Ren, and Re-strengthening of 66 KV lines and Substations i/c Dist. S/stn.-SP

929.96

0.00

0.00

0.00

0.00

929.96

397.46

0.00

Xth Plan

 

TRANSMISSIION TOTAL

11153.96

0.00

1698.00

1370.46

477.54

5807.50

1875.00

25.00

 

II.B

DISTRIBUTION
(Spilled over from the Ninth Plan)

1.

Ren, Re-strengthg. & upgradation of sub-transmission lines and Substations

787.79

0.00

0.00

515.00

272.79

273.00

273.00

50.00

Completed

2.

Conversion of Rabongls and Soreng distribution from O/H to U/G system.

             

20.00

 

3.

Miscl Distribution Schemes

4123.62

0.00

2081.00

3918.64

204.98

205.00

205.00

25.00

Completed

 

DISTRIBUTION-TOTAL

4911.41

0.00

2081.00

4433.64

477.77

478.00

478.00

95.00

 

II.C

ESTABLISHMENT OF TESTING LAB.

100.00

0.00

0.00

0.00

0.00

100.00

100.00

0.00

 

II

TRANS. & DISTRIBUTION (TOTAL)

16166.37

0.00

3779.00

5804.10

955.31

6385.50

2453.00

120.00

 

III

CSS SCHEMES
(Other than generation Schemes)

 

(Ongoing Scheme)

                 

1.

Metering aimed at reformation and restructuring of Power sector- CSS

1638.00

0.00

0.00

1000.00

638.00

638.00

638.00

638.00

2002-03

 

(New Schemes)

                 

2.

Improvement of Subtransmission and distribution under S/W and LLHP.

1425.00

0.00

0.00

0.00

0.00

1425.00

0.00

100.00

2003.04

 

(Under Consideration with MOP)

                 

3.

Remodelling of distribution system in and around Gangtok.

2475.00

0.00

0.00

0.00

0.00

`2475.00

500.00

100.00

2004-05

4.

Improvement of sub-transmission and distribution under East Circle

1500.00

0.00

0.00

0.00

0.00

1500.00

0.00

100.00

2005-06

 

TOTAL

7038.00

0.00

0.00

1000.00

638.00

6038.00

1138.00

938.00

 

IV

NON-LAPSABLE POOL OF CENTRAL RESOURCE

1.

LLHP (12MW) (Non-laps Pool of CF)

1951.00

0.00

0.00

1521.00

430.00

430.00

430.00

430.00

10/2002

2.

Referral Hospital 66/11 KV Substation

50.00

0.00

0.00

50.00

0.00

0.00

0.00

0.00

Completed

3.

VIP complx at GTK State Plan

100.00

0.00

0.00

50.00

50.00

50.00

50.00

50.00

08/2002

4.

132KV lines from Rangit to Meli I/c 2x50 MVA Substation at Melli

3979.00

0.00

0.00

0.00

0.00

3979.00

2950.00

1800.00

Oct 03

5.

66 KV lines from LLHP to Bulbuley

1348.00

0.00

0.00

0.00

0.00

1348.00

300.00

100.00

March ‘04

6.

PLCC Equipments Modernisation and establishment of CLD etc.-SP

849.00

0.00

0.00

0.00

0.00

849.00

300.00

100.00

Dec ‘03

 

NON-LAPSABLE-TOTAL

3277.00

0.00

0.00

1621.00

480.00

6656.00

4030.00

2480.00

 

ABSTRACT

Sl.

No

Name of the Schemes

Estd. Cost (latest)

Cumltve Exp. Upto 3/97

Appd. Outlay IXth Pl.

Actual Exp. IXth Pl.

Spill Over to Xth Plan

Appd. Outlay (2002-07)

Proposed Outlay (2002-03)

Appd. Outlay (2002-03)

I.

GENERATION

12758.79

303.60

3702.00

3443.01

679.74

12092.50

2847.00

1015.00

II.

TRANS. & DISTRIBUTION

16165.37

0.00

3779.00

5804.10

956.31

6385.50

2453.00

120.00

III.

RURAL ELECTRIFICATION

1000.00

0.00

1960.00

750.00

13.10

600.00

150.00

0.00

IV.

CONSTRUCTION OF BUILDINGS

278.00

0.00

500.00

500.00

4.36

250.00

100.00

30.00

V.

SURVEY & INVESTIGATION (S&I)

86.78

0.00

100.00

300.00

1.12

100.00

50.00

5.00

 

CSS COMPONENT (S&I)

23.00

0.00

0.00

21.00

21.00

21.00

11.00

0.00

VI.

DIRECTN & ADMNSTRATION

600.00

0.00

700.00

4422.00

0.00

4422.00

860.00

700.00

VII.

INTG. STUDIES OF TEESTA CAS

1500.00

0.00

0.00

160.00

0.00

160.00

50.00

0.00

 

TOTAL (State Plan)

32387.94

303.60

10741.00

15369.11

1653.63

23900.00

6500.00

1870.00

   

0.00

0.00

0.00

0.00

0.00

100.00

0.00

100.00

 

APDRP

0.00

0.00

0.00

0.00

0.00

0.00

0.00

1800.00

 

PMGY

0.00

0.00

0.00

0.00

0.00

0.00

0.00

400.00

 

TOTAL (STATE PLAN)

32387.94

303.60

10741.00

15369.11

1863.63

24000.00

8500.00

4170.00

 

CSS COMPONENT

28980.50

341.40

1053.50

4495.50

4103.10

24382.50

8439.00

5784.00