ANNUAL PLAN 2002-03
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
4. EXPANSION/LINK ROADS
Rs 883.85 lakhs
Capital: 5054-04.337-60.00.73 Rs
883.85 lakhs
There are some roads which are constructed upto the earthen level under this activity and which need to be taken forward upto WBM level. There are also some roads which are completed upto WBM standard which need to be completed. The bridges in the roads constructed under this programme need to be laid. All these programmes are included under the need.
Following construction of new roads commenced in the year 2000-01 are under progress in 2002-03.
|
Under this scheme following carpeting works are tendered which will commence in 3rd qtr of 2002-03 and will be continued in 2003-04.
|
5. CONST. OF NEW ROADS. Rs
1000.00 lakhs
Capital 5054-04-337-60.00-82 Rs
1000.00 lakhs
Under this scheme new roads are constructed to provide connectivity to remote villages. The nature of activities involved includes road cutting, construction of corss drainage works wherever required, slope stabilisation and development of drainage system.
Following schemes are tendered and will commence in the 3rd quarter of this financial year and will be continued in the year 2003-04.
|
Some more link roads are to be constructed and to be completed in the 10th Plan and they are:
1. Link road between Khaniserbong to Mabong.
2. Link road starting from the appropriate point to Yangang Rangrang road to Lingmo via Majuwa School.
3. Sangmo to Satam
4. Approach road to Lingdum
5. Link Road joining Peku to V.C. Ganju Lama Road.
6. Assangthang to Jorethang.
7. Wok School to Chamchey.
8. Lalturning Golai to Middle Camp.
9. Extension of Road from Tinkitam to village of Baichung.
10. Yangang to Bandey School.
11. Uttarey to Jhankri Dunga
12. Nambu to Upper Rimbik
13. Extension of Phamphok Road.
14. Marchak to Tumlabong.
15. Extension of Sang Khola Zingla road at Sang Martam road at Najitam.
Survey and estimates whenever are ready that would be processed for sanction. It is expected that one or two of these would be started at the fag end of this financial year.
6. REPLACEMENT Rs
86.00 lakhs
Capital 5054-04-337-60.00.72 Rs
86.00 lakhs
Under this head weak bridges are proposed to be replaced by bridges capable to sustain vehicular load of heavy axle loads. Also temporary bridges are proposed to be made to permanent bridges. The weak pavements are proposed to strengthen under this programme.
Under this programme it is expected that replacement of Rangpo bridge also which was constructed year back which is of low load carrying capacity would be started.
7. ADDITIONAL FACILITIES
Rs 70.00 lakhs
Capital head: 5054-04-337-60.00.75
Rs 70.00 lakhs
Under this head development of supporting infrastructure such as storage facilities Mechanical Workshop and their infrastructure and other back up facilities would be covered.
8. MACHINERIES AND EQUIPMENTS Rs
140.00 lakhs
Capital head: 5054-04-337-05.052.00.71 Rs
140.00 lakhs
The above allocation has been kept essentially to augment the Departments fleet of Machineries comprising bulldozers, road rollers.
Road machinery such as Bulldozer, loaders etc. are required for new construction of road and to maintain only mode of transportation and communication function smoothly. The existing bulldozers of the department are far less than the actual requirement and also most of them are quite old. Keeping in view of the overall financial aspects it has been proposed to replace one oldest bulldozer by a new one during 2002-03.
Excavator cum loader is found very useful especially during monsoon to clear road blockage due to minor land slides. Since the machine is tyre mounted its mobility from one place to another is easy without damaging the carpeted roads. At present we have three such machines It is proposed to procure one more for West Division. Carpetting of State roads is being taken up on priority in large scale for which quite a large scale for which quite a large numbers of Road Rollers are required. It is proposed to maintain the fleet of Road Rollers by replacing 4 (four) very Road Rolelrs to cope with the requirement of carpeting works.
Since most of the existing bulldozers are old and need updating and renovation replacement of some major parts especially in the under carriage system is very essential. The renovation of these bulldozers will enhance the Capital value of the Bulldozers. There are also other machineries like wheel loaders, road rollers which are also of old age and they need to be upgradaded by way of major repairs. Provision for this has also been kept.
|
9. MAJOR REPAIRS & RENOVATION: Rs
250.00 lakhs
Capital: 3054-04.337-60.00.73 Rs
250.00 lakhs
The topography of the State is very pronounced and the extent of damages that occur during the monsoon need not be emphasized. Such damages occur in the weak stretches of different roads and such weak stretches abroad in each road of Sikkim. The slope of these weak stretches need to be strengthened and wherever renovations are required, the expenditure on such renovation and slope strengthening are covered under this head.
10. SURFACING STRENGTHENING Rs
108.00 lakhs
Capital Head: 5054-04.337-60.00.81 Rs
60.00 lakhs
11. NABARD Rs
100.00 lakhs
Capital: 5054-04-337-60.60.00.79 Rs
100.00 lakhs
Under this scheme carpeting of following roads were taken up in 2001-02 and are continued in this financial year also.
1. Widening & Carpetting of Ranipool Rumtek Road
2. Carpetting of Legship Tashiding Road.
3. Carpetting of Ranka Sichey Road
4. Carpetting of Tulshi Ram Kashyap Marg.
5. Carpetting of Rimbi Khechiperi Road.
12. AIRPORT Rs
996.00 lakhs
Capital: 5053-02.102-60.00.71 Rs
996.00 lakhs
The DPR submitted by Airport Authority of India is preliminary one and a lot of issues are required to be discussed before it can be finalized. Therefore, a provision of Rs 9.96 crores provided in the current Annual Plan would not be spent fully. Since this grant can be utilized within a period of five years, the unspent money can be rolled over to the next Annual Plan.
13. DPR NH 31A Rs
300.00 lakhs
Revenue: 3054-01.800-60.00.71 Rs
300.00 lakhs
Government of Sikkim has appointed Sikkim Industrial Development & Investment Corporation Limited (SIDICO) as nodal agency for undertaking studies to improve National Highway 31A, who in turn signed a MoU with Infrastructure Leasing and Financial Services Limited (IL&FS) to assess in the development of infrastructure projects. Initially the partnership focus on improving road connectivity between Gangtok and the plains, the project would extend to Nathula.
IL&FS will assess in preparing a detailed project report r this road including suggesting options for its implementation and financing. Prior to undertaking the project IL&FS will do a detailed feasibility study to assess the potential of implementing the project on a commercial format which requires high quality project documentation to enable project to meet bankability requirements.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|